The NGI (Mixed Case) Project work was in the live gas plant of GASCO in Habshan, Abu Dhabi.
OQC performed civil and earth works for Punj Lloyd, including excavation, backfilling, disposal of excavated material, concreting, reinforcing, shuttering, grouting, paving, fencing installation and removal of temporary fence, supply and laying of gatch, soil testing and setting up of access gates.
The work also included asphalt road cutting and restoration, supply and installation of conduit pipes and fire proofing of pipe rack structures.